On 5/5/2018, Misr Chemical Industries Company contracted with the Egyptian Consulting Office for Environmental Consultancy to design an industrial wastewater treatment plant by collecting field data, analyzing discharged water samples and measuring discharge, as well as environmental impact assessment under the supervision and follow up of EEAA. Plan of reconciling the conditions and timetable of the project. For the purpose of achieving full harmonization and full compliance with the Environment Law No. 4 of 94 and amended by Decree No. 9 of 2009 on drainage on the marine environment. The tender documents were finalized on 10/2018 and the project is being prepared to be chosen. The project schedule for the stages of placement and placement, and the stage of graduation and delivery.
Technical studies and And the awarding of tenders. | 3 months from 11/2018 To 1/2019. |
Delivery of the site to the executing company. | 1 month on 2/2019. |
Implementation and Installation. | 5 months from 3/2019 To 7/2019. |
Operating Tests. | 1 month on 8/2019. |
Primary Delivery and Evaluation of station work. | 1 month on 9/2019. |
Total period | 11 months. |